Lane restrictions around Beaverdam

Ohio Department of Transportation announced I-75 lane restrictions begin today in Beaverdam. Crews will be moving barrier wall for the winter traffic pattern.

The following highway construction scheduled to occur within Allen County is dependent upon weather conditions.

Interstate 75 in both directions, at the village of Beaverdam, will have daytime lane restrictions (7 a.m. - 7 p.m.) to move the barrier wall in the work zone. 

The lane restrictions will begin on Tuesday, Dec. 8, or Wednesday, Dec. 9, and continue through Monday, Dec. 11.

The barrier wall on the northbound side will be removed. The barrier wall on the southbound side will be moved and extended along the new shoulder.

Following the relocation of barrier wall, lane restrictions will occur next week to remove and restripe pavement markings for the traffic pattern that will be in place for the winter.

Stories Posted This Week