Work on the hospital's second floor continues next week
Steel erection and framing of the two-story addition at the Bluffton Hospital continues next week. This addition will house the new emergency department and other services. As part of the framing, masonry block installation continues for the interior elevator and stairwell.
Roofing is being finished and interior framing of new walls and hanging HVAC duct work for the new operating room continues.
Work on two emergency exit ramps from our existing building is well under way. One is on the alley (west) side and the other will replace the steps near the medical/surgical exit from the first floor.
Major construction equipment and delivery trucks will continue to cause periodic traffic restrictions. The hospital staff asks that persons drive carefully and protect the safety of the construction workers.
Stories Posted This Week
Wednesday, November 27, 2024
- Happy Thanksgiving from the Bluffton Icon!
- Dec. 6 Handel's Messiah is sold out
- Smoke on the Water: Lung cancer screening guidelines
- Council recap: Village prepares to hire full-time EMS chief, hears "granny flat" legislation feedback
- 2024 Bluffton Blaze of Lights to-do list
- Community Foundation awards $1M in grants
Tuesday, November 26, 2024
Monday, November 25, 2024
Sunday, November 24, 2024
Saturday, November 23, 2024
- Pirate football downs Patriots in Region 22 final
- Owen D. Ziessler worked for Accubuilt
- Weekend Doctor: Complex Regional Pain Syndrome
- Agenda for Bluffton Council on November 25
- Super Cute Dresses ships 10,000 packages via Bluffton Post Office in 2024
- Volunteer opportunities at Bluffton Hospital
- Invitation to provide monthly display at Bluffton library