ER roof nears completion

Here's an update on Bluffton Hospital construction for a short work week of Nov. 22:

New Emergency Department
. The installation of roof is nearing completion
. Fireproofing is underway
. Temporary windows are being installed to enclose the area for winter
. The air handlers for the Emergency Department and Surgery areas are being prepared to use
. Brick installation continues as exterior walls are constructed
. Steel for the Emergency Department canopy is being installed
. Work continues on metal studs, exterior eyebrow and dens glass installation

Lot behind the existing hospital
. Concrete pads to hold the propane tanks, oxygen tanks and generator have be poured
. Work is underway on the storm sewer and waterline in the new Emergency Department parking lot
. Site work in the Emergency Department parking lot is underway
. Steel is being erected on the rear ramp

New Surgery Area
. Ductwork and electrical conduits continue to be installed
. Metal stud and drywall work continues for interior walls

For your safety and the safety of our contractors, all associates and visitors should refrain from entering the work site at any time without prior authorization and without appropriate safety equipment. Tours of the construction site must be scheduled and must be conducted by a construction team escort.

Stories Posted This Week