Village hopes voters will fix Bluffton's "rust belt" by passing tax levy on March 6
There's a rust belt in Bluffton. It's mostly on streets with water mains that were installed between 1920 (or earlier) and the late 1940s. There are lots of street in the category. They are familiar sounding: Grove, Lawn, Kibler, Jackson, Cherry, Mound and Washington.
In addition, there are some newer lines in need of replacement. Those include Sunset Drive and Garmatter Street.
The village wants to correct the problem. The solution proposed is a one-quarter percent income tax exclusively for water and sewer capital improvements. If Bluffton voters pass the tax on March 6 it will replace the town hall quarter-percent income tax that will expire on Dec. 31.
The tax will continue for 15 years and will fix a $4 million problem under our feet. The first of two community meetings created to answer questions about the proposed tax took place on Feb. 23. The final meeting is at 7:30 p.m., Thursday, March 1, in the town hall.
The lines on the list to be replaced are mostly 4-inch cast iron lines. As evident in the photos, the lines are in fragile condition. The replacement lines are 8-inch, which will not only improve water quality and flow, will enhance the village's fire rating.
Background
In November 2005, the citizens of Bluffton voted to enact a 1/4 % income tax for 10 years to pay for the renovations of the town hall. This 1/4 % income tax generated $342,000 in revenue in 2011. The project will be paid for by Dec. 31, 2012, and the 1/4 % income tax will be removed nearly four years earlier than expected.
According to village officials, if approved by the voters, this will result in Village of Bluffton taxpayers paying the same income tax rate in 2013 as 2012 on the same type of taxable income. Unearned and retirement income will continue to be exempt from taxation.
The Bluffton water system was constructed in 1896 with three miles of water mains. While records are insufficient to determine exact dates of line installations and replacements over the years, the cast iron lines now in service are well beyond their expected life of 40 to 50 years.
As is evidenced by sections of water main recently removed in repair of waterline leaks, over time iron deposits accumulated in the lines and over-coated with mineral deposits from the villages old well water.
The new water from Ottawa does not have the high mineral content that our old water had and the mineral deposits have been dissolved, leaving behind the iron deposits to produce rusty water in the system.
Water customers on the newer plastic water lines do not have rusty water unless it is coming through the system from older lines. The solution is to replace the old cast iron waterlines with new plastic water lines.
The estimated cost to replace the most affected areas of the village is $1.5 million. These areas have experienced the most pronounced discoloring of water since the water system change.
If the 1/4 % income tax is passed March 6, 2012 the village will have a dedicated revenue source to support the borrowing of the cost to replace this aging infrastructure.
The initial projects include the replacement of water mains in the Jackson Street-Grove Street-Lawn Avenue area, the Mound-Cherry Street areas, and the looping of the water main serving Sunset Drive.
These projects could be completed in 2012. After the effects of the new lines are analyzed, other areas may need attention.
Other water and sewer concerns are the continued work on maintaining and upgrading the sanitary sewer system. The sewer plant and collection system were constructed in the early1950s and the sewer plant was reconstructed in 2003.
The cost of replacement for the aging sanitary sewer collection system will be substantial. The 1/4 % income tax would help with these projects in the future.
Given that state funding, which formerly contributed $350,000 annually to village revenues, is rapidly being eliminated, it is not feasible for the Village of Bluffton to continue to subsidize water and sewer infrastructure projects with General Fund revenue.
Ballot language
"Shall the ordinance proposing a 1/4 % levy on income for the purpose of water and sewer capital improvements only (replacing the existing 1/4 % income tax for town hall improvements), commencing January 1,2013, for a period of years not to exceed 15, be approved."
Stories Posted This Week
Thursday, November 28, 2024
Wednesday, November 27, 2024
- Happy Thanksgiving from the Bluffton Icon!
- Dec. 6 Handel's Messiah is sold out
- Smoke on the Water: Lung cancer screening guidelines
- Council recap: Village prepares to hire full-time EMS chief, hears "granny flat" legislation feedback
- 2024 Bluffton Blaze of Lights to-do list
- Community Foundation awards $1M in grants