West Elm Street project starts in early October
Roadwork will begin on the West Elm Street project in early October, according to Jesse Blackburn, village administrator. The project covers Elm from Spring to Rosenberger Drive.
Blackburn brought Bluffton council members up to date on the project on Sept. 10.
The project has two phases.
• Water work phase
October to December –
• Installation of an 8-inch water main, creek crossing, new service lines, new meter settings where required and new fire hydrants.
• Trenches from work performed will be temporarily paved, road is planned to be closed during construction, maintained for local traffic.
• Street work phase
March to June 15, 2019 –
Complete road reconstruction, sidewalks, curb, 4-foot tree lawn between sidewalk and curb and installation of catch basin.
Stories Posted This Week
Friday, March 21, 2025
Thursday, March 20, 2025
- Bluffton Beavers sports roundup, March 12-18
- “Bound to Remember 500 Years of Anabaptist Critique” is March 25 Forum
- Adrenaline rush: Introducing neffy®
- Joyce E. Pugsley was a nursing assistant
- Village and county updates on March 2025 Bluffton chamber agenda
- MHCO hosts an afternoon of music, March 22
Wednesday, March 19, 2025
Tuesday, March 18, 2025
- Elvet Foulkes served in the U.S. Army
- Awakenings victim outreach program receives grant
- "Outside the Lines" exhibit showcases Bluffton University art students
- Public invited to weigh in on the future of transportation in Ohio
- Village of Bluffton Income Tax filing information
- Donald M. Unterbrink worked for Ford Motor Co.
- Bluffton Community Dog Park is dedicated in memory of teacher Katrina Riepenhoff