You are here

Framing of hospital addition nears completion

Several projects are on the construction schedule at Bluffton Hospital this week. Those projects follow:

  • Framing of the two-story addition is nearing completion.. Masonry work continues on the stairs and elevator near the new Emergency Department.
  • Masonry work has begun next to Harmon Road.. Air handlers have been set in place over the new Surgery area.
  • The new boilers have been installed and will be inspected by the state. Once they are certified by the state, they will be tested for two weeks and then the old boiler will be removed.