Jefferson Street nears completion

Bluffton council will get an update on several village projects at Monday’s council meeting.

Among items on the agenda include:
• The Jefferson Street bridge will be grooved on Tuesday, as the asphalt was installed today. Also, on Tuesday will be street line striping. Once completed the roadway will open.

• New playground equipment for the Buckeye park playground arrived last week. It will be installed on Tuesday.

• Leaf pick up will begin this week.

• Twenty-six ADA curb ramps were completed in the village in 2019.

• A priority list for sidewalk evaluation is underway.

• Phase II (2020) of the Jefferson Street improvement project will include meetings with property owners – to be scheduled this week.

• Discussion of State and U.S. Bike Route System through Bluffton.

These and other items on the agenda are in the council packet attached at the bottom of this story.

Stories Posted This Week